The newly inaugurated Palava Bridge in Maharashtra, built to ease traffic congestion, was shut down within hours due to safety hazards
From Promise to Peril: The Bridge That Couldn’t Hold
On July 4, 2025, the Palava Bridge also known as the Katai-Nilje Flyover was inaugurated by Shiv Sena MLA Rajesh More in a low-profile ceremony. Marketed as a vital link to ease congestion between Shilphata and Kalyan, the ₹250 crore project was expected to reduce travel time from 45 minutes to 10 minutes.
Table of Contents
Instead, within two hours of opening, the bridge was shut down due to multiple skidding incidents, including injuries to two bikers. Commuters quickly dubbed it a “skidding zone”, citing loose gravel, muddy patches, cement spills, and poorly laid tar as serious safety hazards.
The bridge’s surface lacked a proper mastic asphalt layer, exposing iron rods and creating deep grooves. Over 450 meters of the 562-meter stretch showed signs of poor construction, prompting emergency patchwork by MSRDC contractors.
Political Firestorm: Blame, Backlash, and Bureaucratic Evasion
The bridge’s rapid deterioration ignited a political storm. Opposition leaders from the Thackeray-led Shiv Sena and Maharashtra Navnirman Sena (MNS) accused the ruling Shinde faction of inaugurating an incomplete and unsafe structure for electoral optics.
Former MNS MLA Pramod Ratan Patil posted viral videos showing potholes and washed-away gravel, demanding a structural audit and criminal action against contractors. Dipesh Pundlik Mhatre, another opposition leader, submitted a memorandum to the DCP, citing injuries and demanding accountability.
Adding fuel to the fire, Deputy CM Eknath Shinde chose to travel by helicopter during his Ashadhi Ekadashi visit, avoiding the bridge altogether. Critics slammed the move, suggesting he was aware of the bridge’s poor condition.
In defense, MSRDC claimed the slipperiness was due to oil from fresh asphalt, and that grit was spread to improve traction. However, commuters and netizens weren’t convinced, calling the bridge a “₹250 crore construction site”.
Eight Years, Endless Delays: Anatomy of a Failed Project
Construction of the Palava Bridge began in December 2018, with plans for two parallel flyovers connecting Desai Naka to Katai Naka. Work was halted in 2020 due to the Dedicated Freight Corridor (DFC) expansion by Indian Railways, which required design revisions.
Despite multiple promises from MP Shrikant Shinde to MLA Rajesh More the project faced repeated delays. Protests erupted over encroachments, budget escalations, and missed deadlines. The final inauguration came after seven years, only to reveal glaring flaws.
The bridge, supported by 45 pillars, was meant to transform the Kalyan-Dombivli-Thane-Navi Mumbai corridor, notorious for traffic snarls. Instead, it became a symbol of administrative negligence, poor planning, and alleged corruption.
Conclusion:
The Palava Bridge fiasco is a sobering reminder that infrastructure isn’t just about budgets and blueprints it’s about accountability, safety, and public trust. As Maharashtra reels from this ₹250 crore embarrassment, citizens demand more than patchwork fixes. They want answers, audits, and assurance that progress won’t come at the cost of lives.